Where 45 days actually go

Forty-five days sounds like one number. On the floor it is seven overlapping stages, three of which can slip without anyone noticing until the booking is missed. Here is the schedule we run on a 1,000-chair order.

Published by JPChairs · Chair manufacturer in Foshan, China · 2026-10-15

The 45-day schedule, stage by stage

These are working days, not calendar days, and they start the day the deposit clears and the specification is frozen. A 1,000-unit mixed order of side chairs and armchairs breaks down like this:

Note the overlaps. Upholstery starts before finishing ends. Drawn as seven sequential blocks the same schedule reads 60 days, not 45.

What a sample adds, and what it saves

Pre-production samples take 10 to 15 days to build and 3 to 5 days to ship. Sampling is the only stage that reliably removes time from the back end, because it turns a thread of emails into an object everyone can measure.

Record six things when it arrives and confirm them in writing: seat height to 1 mm, seat depth, back angle, foam firmness, fabric colour under a D65 light box, and finish sheen. A buyer who approves a sample verbally and then asks for a 20 mm lower seat on day 20 loses the slot.

Sample cost is normally USD 120 to 350 per chair plus express freight, and it is credited against the order on most programmes. The alternative is a container that arrives wrong, which costs 45 days plus the freight.

The five delays that push 45 days to 70

Wood, metal and upholstery: why the numbers differ

Solid beech frames sit at 40 to 50 days because timber has to dry and finish. Welded and powder-coated steel frames are 30 to 35 days. Fully upholstered shells on metal frames are 35 to 45 days, dominated by fabric and foam rather than by the frame. Banquet chairs with a ganging device and a trolley add 5 to 7 days for the hardware.

Mixing three frame types in one container does not mean the schedule is set by the slowest item. It means the packing date is set by the slowest item, and everything else sits in the warehouse for up to 15 days. If the opening date is fixed, ship the slow line first.

Booking, cut-off and the ten days nobody budgets

Production ending is not the same as the container leaving. Between the last carton and the bill of lading there are four fixed dates:

Book space at least 14 days before the expected ready date. A booking is free to move; a missed one costs a week.

How to shorten the schedule honestly

Three things genuinely compress a schedule, and none of them touch quality:

What does not work: skipping the 24-hour finish cure, or asking for inspection on the loading day rather than three days before. Both buy one day and risk thirty.

The shop-floor capacity and production calendar behind these numbers are described on the factory production calendar, and the frames we build to them are in the commercial restaurant chairs.

Questions buyers ask

FAQ

How long does a 1,000-chair factory order take?

45 working days from cleared deposit to loaded container for a standard frame with stocked fabric. Add 10 to 15 days for a pre-production sample and 20 to 25 days if the fabric has to be milled to order.

Can a chair factory deliver in 30 days?

Yes on a repeat order with stocked materials and a standard finish, in low season. It is not realistic for a first order, a custom finish, or anything placed within six weeks of Chinese New Year.

When should I place an order for a hotel opening?

Count back from the installation date: 30 days transit, 45 days production, 15 days sampling and 20 days if the fabric is milled to order. That is 110 to 120 days, or 140 days if the schedule crosses February.